Kingsfield Court | Leicestershire

Trident’s Leeds office was instructed to undertake project monitoring services for the construction of a new 70-bed care home in Earl Shilton, Leicester.

Trident’s involvement with this project included attending monthly site meetings to review the progress of works and ensure it was in line with client’s desires as well as the official programme. These meetings often resulted in the Leeds team producing progress reports for the client.

Other tasks included reviewing contractors’ valuations and producing corresponding drawdown schedules and liaising between the contractor and the employer’s agent to ensure all queries had been answered.

Trident made use of their PropTech offering by undertaking both ‘dollhouse’ and eye-level scans of the key areas of the newly completed care home. This was made possible with our 3D Matterport scanning camera.

The 3D models were well received by the client and incoming tenant, who has subsequently used them for marketing purposes.

Click through to see a selection of 3D models of Kingsfield Court:

Client

Target Healthcare

Our Role

Project Monitoring

Key Issues

  • Monthly site meetings held to review construction progress.
  • Being constantly cautious of moving vehicles within the construction site.
  • Liaising with the employer’s agent and main contractor to ensure the smooth running of the project.
  • Producing a drawdown following the contractor’s valuation.